• Refine Search

  • All Results

WELLS STREET BRIDGE OVER THE MILWAUKEE RIVER REHABILITATION PROJECT

CONSTRUCTION UPDATE-JUNE 2019

Due to colder than normal weather last fall, some work for the bridge project was postponed. The contractor plans to finish the remaining work during the week of June 10th, weather permitting. Expect lane shifts over the bridge to occur on Monday and Tuesday for the contractor to seal the bridge deck with a polymer overlay. One lane of traffic in each direction will continue to be maintained.

The Wells Street Bridge be fully closed to traffic and pedestrians beginning Wednesday, June 12th and is anticipated to be re-open on Friday, June 14th by the evening. Local access to adjacent businesses and properties will be maintained. During this closure, the contractor will finish concrete staining of the piers under the bridge and will conduct final testing of the electrical system.  


PROJECT OVERVIEW

The Wells Street Bridge over the Milwaukee River, located between North Water Street and North Plankinton Avenue, will be closed for rehabilitation. The vertical lift bridge was built in 1985 and is one of the main arteries that connect Milwaukee's Downtown and Westown neighborhoods.

The work will upgrade structural, hydraulic, mechanical and electrical components and replace curbs, gutters and sidewalk slabs as necessary due to condition or grade change. 

When completed, the bridge will provide for an 11-foot driving lane in each direction and add bicycle plating to accommodate bicyclists in each direction. New traffic railings will be installed on the sidewalk near the curb for pedestrian safety. Outer railings will remain the same. 

The Wells Street Bridge will be closed to pedestrian and vehicular traffic for the duration of the project.

WHAT TO EXPECT DURING CONSTRUCTION
 

The City of Milwaukee works to minimize impact for businesses, residents and the traveling public during construction.

Construction Hours: Construction work is allowed from 7:00 a.m. to 9:00 p.m. The operation of any motorized equipment will not be allowed between 9:00 p.m. to 7:00 a.m. without prior written approval. Work over weekends and holidays will be allowed with department approval.

Contractor: Zenith Tech, Inc.

Traffic Detour Route: Vehicular traffic will be re-routed to the Kilbourn Avenue bridge from N. Broadway on the east side of the bridge, and from N. Old World Third Street on the west side of the bridge. 

Parking Information: There will be no on-street parking available on Wells Street between North Plankinton Avenue and North Water Street during construction.

Pedestrian Access: Although no pedestrians will be allowed to travel over the bridge during construction, pedestrians will be able to travel to those properties and businesses that abut the bridge during construction, with the least amount of inconvenience. A detour route will guide pedestrians to the two nearest bridges, Kilbourn Avenue and Wisconsin Avenue bridges.

Riverwalk Access: The Riverwalk will be closed at the bridge to pedestrians to accommodate construction. Other areas of the Riverwalk will remain open.

Boat Access: The Milwaukee River navigation channel will remain open during construction.


PROJECT CONTACTS
Tony Kotecki Construction Supervisor [email protected] 414-708-3886
Megan O'Connor Support for Business Liaison [email protected] 414-708-1433

 

 

 

Start Date: March 5, 2018
Anticipated Completion: November 2018

*All work is weather dependent and subject to change

Construction Update:
August 2018
June 2018
April 2018

Project Overview-Printable Version
Traffic Detour Map​​​​-Printable Version

Public Involvement Meetings:
The City of Milwaukee Department of Public Works conducted two public invovlement meetings to receive input and share project details with residents and businesses located in the project area.

September 28, 2016
City Hall 
200 East Wells Street, Room 301-B
6:00 - 8:00 p.m.

September 28, 2017
Frank P. Zeidler Municipal Building
841 North Broadway
Room 102
4:30 - 6:30 p.m.

The project is funded and managed by the Wisconsin Department of Transportation in conjuction with the City of Milwaukee Department of Public Works. 

This site is powered by the Northwoods Titan Content Management System

Menu

X