Phase 2 of the North Teutonia Avenue reconstruction project began in April 2016.  The project will consist of removing existing roadway and replacing it with concrete pavement while widening the roadway.  All curbs, gutters and driveway approaches will be replaced. Sidewalks will be replaced as necessary due to grade and condition.  The project is scheduled to be completed in July 2016, weather permitting.

April 2016 update - click here

November 2015 update - click here

August 2015 update - click here

Project information - click here

Bus route detour map: click here

 

For more information on this project, please contact Cecilia Gilbert:                                  

Phone: 414.286.3318 
Email:  [email protected]


 

 

 

 

 

 

 