• Refine Search

  • All Results

NORTH HOLTON STREET BRIDGE REHABILITATION PROJECT

ATTENTION: As of February 2025, this project page will now be maintained on EngageMKE at the URL engage.milwaukee.gov/holton-bridge.

  • OVERVIEW
  • PROJECT UPDATES
  • COMMUNITY MEETINGS & DOCUMENTS
  • CONTACT US

OVERVIEW

The City of Milwaukee Department of Public Works and Wisconsin Department of Transportation are conducting a rehabilitation project on North Holton Street Bridge over the Milwaukee River from a point north of East Brady Street to East Glover/Reservoir Avenue. The North Holton Street Bridge was constructed in 1926, rehabilitated in 1987-1988, and has become structurally deficient. Around 10,200 vehicles travel over this bridge per day. 

 

SCOPE OF WORK 

The proposed rehabilitation throughout all three phases will consist of the following activities: 

  • Substructure work including structural steel repairs to select bents (otherwise known as piers or substructure units), girder repair at select bents, concrete substructure repairs to all bents, and stairway replacement at one location.    
  • Structural steel repairs to superstructure including main girders, floor beams, stringers and trusses.   
  • Installation of new expansion joints on bridge deck. 
  • Painting of all bents and superstructure.  

 

PROJECT SCHEDULE

Construction will take place in three phases over three years. Each phase is designed separately and will be approximately one year long.

Phase 1 (2023-24): Expansion joint replacement and repairs to the concrete deck. Steel repairs and painting to the substructure from the river to the south end of the bridge.

Phase 2 (2024): North abutment concrete and stone repairs. Steel repairs and painting to the substructure from the river to the north end of the bridge.

Phase 3 (2025): Steel repairs and painting of the superstructure for the entire length of the bridge. 

 

FUNDING

The estimated total cost of all 3 phases is $12.7 million. Estimated cost of Phase 1 is $5 million. Federal aid will pay for 80% of the cost, and the City will pay the remaining 20%. No property assessments are currently anticipated as part of this project. 

MAP

CONSTRUCTION UPDATES

Project Update - November/December 2024

The North Holton Street Bridge is open to bike, pedestrian and vehicle traffic. 

  • Weekend work has concluded. 
  • Sandblasting and painting operations have concluded until spring 2025.
  • Work will continue under the bridge as weather allows to complete repair operations.


Construction Forecast - Late October-early November 2024:

Crews will continue sandblasting and painting operations.

  • Weekend work is scheduled through late November to complete this part of the project.
  • The bridge will continue to be closed to traffic through early winter 2024.

Holton Street Bridge Forecast for November 2024

 

Construction Forecast - September-early October 2024:

The N. Holton Street Bridge will continue to be closed to traffic for painting and sandblasting the bridge structure.

  • Businesses and residents should be aware that noise and dust will be associated with this work. Steps are taken by the project team to minimize these effects.
  • Crews may be working throughout the weekends to complete this work. 

Marsupial Bridge, located under the N. Holton St. bridge, will remain open during this work. 


September 27 Construction Forecast


Construction Update - Beginning August 5, 2024: 

The North Holton Street Bridge will be closed to all traffic while the project team continues bridge restoration operations. The bridge is expected to remain closed through Fall 2024.

  • Motorists are encouraged to use Pleasant Street and Humboldt Avenue to cross the Milwaukee River.
  • The Marsupial Bridge, located under the North Holton Street Bridge, is expected to intermittently close August 5 through August 7. 

Holton Street Bridge - August 5, 2024 Closure


Project to Resume - Beginning Monday, May 13:

The project team is scheduled to begin bringing equipment, including barges, on-site for Phase 2 of the North Holton Street bridge rehabilitation project. 

Holton Street Bridge Update May 10, 2024


Project to Resume - Beginning May 2024:

Traffic on the North Holton Street bridge is schedule to shift to the southbound lanes.

  • Bidirectional traffic will be maintained.

After the Republican National Convention (July 15-18) through late October, the North Holton Street bridge is schedule to fully close while crews work on the North abutment. 

Holton Street Bridge Phase II Overview March 28. 2024


Project Overview - October 2023 Overview: 

The 2023 construction season is making great progress! Here's what's happening on the North Holton Street bridge rehabilitation project during the month of October to wrap things up before the winter!


Project Update - Monday, September 18, 2023:

Commerce Street, beneath the north Holton Street bridge, is scheduled to be reduced to one lane. Flaggers will be at the closure directing traffic. 

Tuesday, September 19 and Wednesday, September 20, 2023:

Commerce Street, beneath the North Holton Street bridge, is scheduled to close while crews perform overhead joint demolition and removal of concrete haunches.


Project Update - Beginning Tuesday, September 12:

The following closures are scheduled to begin while crews work on overhang and joint demolition. Closures are anticipated to last for approximately two weeks and to take place between 7 a.m. and 6 p.m.

  • South Riverwalk
  • Marsupial Bridge 

Tuesday, September 19:

Parking on Commerce Street will not be allowed during overhang demo. 

 

COMMUNITY MEETINGS & DOCUMENTS

The City of Milwaukee is scheduled to hold a business and resident meeting regarding phase 2 of the North Holton Street bridge rehabilitation project on Thursday, March 28, 2024, in the Lakefront Brewery parking lot (1872 N Commerce Street). You may attend anytime between 4 and 6 p.m.


The City of Milwaukee, in partnership with the Wisconsin Department of Transportation (WisDOT), held a business and resident meeting regarding the North Holton Street bridge rehabilitation project on Tuesday, April 25, 2023, from 4:30 to 6:30 p.m. at Swing Park (1737 N. Water Street).”

 

The City of Milwaukee Department of Public Works holds public involvement meetings to receive input and share project details with residents and businesses located in the project area. 

Virtual Public Involvement Meeting  - January 12, 2022 from 4:00 to 6:00 pm 
Presentation was provided at 4:00 p.m. and at 5:00 p.m.

CONTACT US

Public Involvement Team
414-255-5658
[email protected]

 


 

 

 

 

Sign up to receive project updates in your inbox!

Name 

Email

 

This site is powered by the Northwoods Titan Content Management System

Menu

X