NORTH LOVERS LANE BRIDGE 
REHABILITATION PROJECT 
OVER UNION PACIFIC RAILROAD

  • CONSTRUCTION UPDATES
  • OVERVIEW
  • WHAT TO EXPECT DURING CONSTRUCTION
  • COMMUNITY MEETINGS & DOCUMENTS
  • YOUR FEEDBACK & COMMENTS
  • CONTACT US

CONSTRUCTION UPDATES 

We aim to provide construction updates every two weeks throughout the duration of the project. Updates will be posted here and sent to those who have signed up through the project website. All work is weather dependent and subject to change. 

Start Date: July 19, 2021
Anticipated Completion: Early December 2021


DECEMBER

  • The contractor has been working on minor, punchlist items throughout the month of December. The North Lovers Lane bridge rehabilitation project will be complete by the end of this week, with equipment removed and shoulder lanes open. Thank you for your patience throughout this construction project. Posted 12/21/21

NOVEMBER

  • Traffic on North Lovers Lane Bridge is in the permanent configuration as of November 23rd. Guardrail installation and landscape restoration will begin the week of November 30th. Crack injection and surface repairs on the underside of the bridge continue into December. Posted 11/23/21
     
  • As of November 8th, one lane of traffic in each direction is maintained on the west side of the bridge. The contractor will begin work on the east side of the roadway which consists of removing, grading and pouring concrete for the approach slabs, paving a segment with asphalt, shaping the shoulder lane, and installing the guardrail over the next two weeks. Once completed, traffic will switch to the permanent configuration while the contractor finishes the shoulder work and guardrail installation on the west side. Crack injection and surface repairs on the underside of the bridge continue through the end of this month. Posted 11/11/21

OCTOBER

  • Traffic will switch to the west side of the bridge starting tomorrow afternoon (10/28), allowing one lane of traffic in each direction. The contractor plans to remove, grade and pour the approach slabs, shape the shoulder lane, pave the east side of the roadway, and install the guardrail over the next two weeks. Slope paving beneath the bridge structure on North Lovers Lane will be finished this week. Crack injection and surface repairs on the underside of the bridge continue into early November. Posted 10/27/21
     
  • The North Lovers Lane bridge deck and curb on the west side has been poured and sealed. The roadway approaches are being removed and the contractor plans to pour concrete for the new approach slabs early next week. Crews have started the removal and replacement of slope paving beneath the bridge structure. Crack sealing on the underside of the bridge deck, abutments and piers will continue into next week. Toward the end of October, traffic will switch to the west side of the bridge. Posted 10/14/21

SEPTEMBER

  • Traffic control on North Lovers Lane Bridge was switched to the east side of the bridge on September 27th, maintaining one lane of traffic in each direction. The contractor has completed the milling operation on the west side of the bridge and is currently preparing the deck for concrete early next week. Following the deck pour, the contractor will remove and replace the roadway approaches during the week of October 11th. Posted 9/30/21
     
  • Deck preparation for this current construction stage on North Lovers Lane Bridge has been completed. The contractor will pour the concrete overlay in the center lanes and seal the bridge deck, which is anticipated to be completed next week. During the last week of September, traffic control will be switched to have two-way traffic, one lane in each direction, on the east side of the bridge while the west side of the bridge is closed. Posted 9/16/21
     
  • The construction staging and traffic control on North Lovers Lane Bridge is scheduled to change on September 2nd. The new traffic pattern will allow one lane of traffic in each direction on the respective sides of the bridge while the center lanes are closed. Both sidewalks will be open to pedestrians. Following the holiday weekend, the existing pavement in the center lanes will be removed. During the week of September 13th, the contractor will prepare the deck for a new concrete overlay. Posted 9/1/21

AUGUST

  • The contractor plans to pour the concrete overlay for the east side bridge deck on Lovers Lane early next week (8/23). Once completed, crews will remove the concrete roadway approaches and grade the area. They will also adjust and rebuild storm sewer inlets to match the new approach slab elevation. The concrete for the new approach is scheduled to be poured in early September. Posted 8/18/21

JULY

  • The temporary asphalt shoulder work on North Lovers Lane bridge was finished on July 26th. Traffic control for Stage 1 of construction will be installed on Tuesday, July 27th. The west side of the bridge will be open to two-way traffic, one lane in each direction, while the east side of the bridge is closed. The sidewalk on the west side will remain open to pedestrians. Later in the week of July 26th, the contractor will mill (remove) the existing pavement on the bridge deck and will prepare the deck for a new concrete overlay in early August. Posted 7/27/21
     
  • During the week of July 19th, crews will install erosion control, set up traffic control equipment, and will resurface the southbound shoulder with temporary asphalt prior to stage 1 of construction. Posted 7/15/21 

OVERVIEW

The City of Milwaukee Department of Public Works (DPW) and the Wisconsin Department of Transportation (WisDOT) are conducting a rehabilitation project to improve North Lovers Lane Bridge over Union Pacific Railroad, which was originally built in 1970. About 9,000 vehicles per day travel on North Lovers Lane Road. 

The work will consist of concrete surface repairs to the existing bridge components, placement of concrete overlay on the bridge’s driving surface, resurfacing about 100 feet of the roadway approach with asphalt on each side, and installing guard rails. The gravel shoulder within the limits of the project will be reconstructed. Curb and gutter, concrete sidewalk and bicycle lanes will be considered for construction to replace the existing gravel shoulder when North Lover Lane Road is scheduled for improvement.

The existing bridge deck will be removed and constructed in three stages to keep North Lovers Lane Road open for two way traffic during construction. 

FUNDING

The bridge structure and limited portion of the roadway impacted by the construction of the bridge will be funded 80% with Federal/State aid and 20% by the City of Milwaukee. There are no assessments to property owners at this time. 

MAP

WHAT TO EXPECT DURING CONSTRUCTION

START: July 19, 2021
COMPLETION: Early December 2021

TRAFFIC STAGES
Stage 1: The west side of the bridge will be open to two-way traffic, one lane in each direction, while the east side of the bridge is closed for construction. The sidewalk on the west side will remain open to pedestrians.

Stage 2: The east side of the bridge will be open to two-way traffic, one lane in each direction, while the west side of the bridge is closed. The sidewalk on the east side will remain open to pedestrians.

Stage 3: The center lanes of the bridge will be closed. One lane of traffic in each direction will be maintained on respective sides of the bridge. Both sidewalks will be open to pedestrians. 

DRIVEWAY ACCESS
Access to adjacent properties will remain open. 

PARKING INFORMATION
On-street parking is restricted. 

BUS ROUTE
Milwaukee County Transit System bus route service is not impacted. 

CONSTRUCTION HOURS
Work is allowed Monday - Friday from 7:00 a.m. to 9:00 p.m.

COMMUNITY MEETINGS & DOCUMENTS

A traditional Public Information Meeting was not be held due to the potential health risks associated with COVID-19. Surrounding property owners were notified of the project through a mailing with comment forms. 

CLOSED FOR COMMENTS

 

PROJECT CONTACTS 

Mike Patti, Project Manager
[email protected]
414-305-7172

Musa Abu-khader, Construction Supervisor
[email protected]
414-708-2529

Megan O'Connor, Project Liaison
[email protected]
414-708-1433

 

Sign up to receive project updates in your inbox!

Name 

Email 

This site is powered by the Northwoods Titan Content Management System

Menu

X