16TH STREET BRIDGE OVER THE MENOMONEE RIVER

ATTENTION: As of February 2025, this project page will now be maintained on EngageMKE at the URL engage.milwaukee.gov/16th-street-bridge.

  • OVERVIEW
  • COMMUNITY MEETINGS & DOCUMENTS
  • YOUR FEEDBACK & COMMENTS
  • CONTACT US

OVERVIEW

The City of Milwaukee Department of Public Works and Wisconsin Department of Transportation are planning to rehabilitate Unit 14 of the 16th Street Viaduct over the Menomonee River. Improvements to the 1929 bridge will be made to the existing structural components. The original bascule bridge will be converted to a fixed bridge and the project will remove the original electrical and mechanical equipment. The work will meet all state and federal requirements, and maintain the unique, historically-significant aspects of the structure.  

PROJECT SCHEDULE

We are anticipating a design completion in February of 2025. Construction is tentatively scheduled to begin in the summer of 2025 and be completed by the fall of 2026.  

PROJECT GOALS

  • Rehabilitate the existing structure
  • Make travel safe and comfortable for everyone by providing a solid surface across the deck

PROJECT FACTS

  • Open grid steel deck will be replaced with a solid surface concrete deck to match the other segments of the viaduct 
  • New structural steel elements will be installed throughout structure 
  • Electrical and Mechanical Systems will be removed, creating a permanently fixed bridge

FUNDING

The construction project is funded through the Wisconsin Department of Transportation Local Bridge Program and includes 80% State and 20% City funding.  

MAP

16th Street Bridge Project Map

 

COMMUNITY MEETINGS & DOCUMENTS 

Materials from Public Involvement Meeting (PIM) #1 - Thursday, December 14, 2023

PIM #1 Presentation

PIM #1 Handout - English 

PIM #1 Handout - Spanish

Materials from Public Involvement Meeting (PIM) #2 - Tuesday, June 18, 2024 

PIM #2 Invite - English

PIM #2 Invite - Spanish

PIM #2 Handout - English

PIM #2 Handout - Spanish

PIM #2 Presentation

Business Outreach Flyer - November 8, 2024

CONTACT US

Sarah McClanahan, Marketing & Communications Officer

[email protected]

414-286-3318

 

Jonathan Thomas, PE, Structural Design Manager

[email protected]

414-286-0463

Let us know where you see issues and opportunities for improvement on 16th Street Bridge over the Menomonee River. Your input will help shape how the bridge looks and will help identify solutions to make the bridge safer and more enjoyable for walking, bicycling, and driving. 

Name 

Address

Email 

Comment box

Sign up to receive project updates in your inbox!

Name 

Email 

This site is powered by the Northwoods Titan Content Management System

Menu

X