Office of African American Affairs
Affordable land and leasing costs, abundant fresh water, an educated workforce, low business costs and easy access to financing, technical assistance and efficient transportation have helped local businesses succeed and grow.
Find information about things to do and happenings in the City of Milwaukee.
Department of Public Works
The Department of Public Works will conduct a rehabilitation project on West Cameron Avenue bridge over the Lincoln Creek. Work began in mid-June and is anticipated to be completed at the end of October 2021. All work is weather dependent and subject to change.
Traffic: West Cameron Avenue will be closed to thru traffic between North 31st Street and North 30th Street for both motorists and pedestrians. Traffic will be maintained on North 31st Street and North 30th Street.
Driveway Access: Driveway access to residential properties and businesses will remain open.
Parking Information: On-street parking within the project limits will be restricted throughout the duration of the project.
Bus Route: There are no impacts to MCTS bus routes.
Construction Hours: Work is allowed Monday - Friday from 7:00 a.m. to 9:00 p.m.
We aim to provide construction updates every two weeks throughout the duration of the project. Updates will be posted here and sent to those who have signed up through the project website. All work is weather dependent and subject to change.
Start Date: June 14, 2021 Anticipated Completion: End of October 2021
OCTOBER
SEPTEMBER
AUGUST
Bearing pads and wood decking on West Cameron Avenue bridge were installed last week. The contractor is currently installing shear studs and rebar in order to pour the concrete bridge deck by August 20th or early in the week of August 23rd. Following the deck pour, crews will form and pour the sidewalk and light blisters. The light blisters are the supports for the street lights on the bridge. The installation of the bridge joint cover plate is scheduled for early September. Posted 8/19/21
JULY
JUNE
Megan O'Connor Project Liaison [email protected] 414-708-1433
Mary Pyritz Project Inspector [email protected] 414-221-0088
Lynn Des Jardins Construction Supervisor [email protected] 414-708-3885
Name
Email
You will receive a confirmation email. Thank you!