Bookmark and Share

WEST WELLS STREET RESURFACING PROJECT

CONSTRUCTION UPDATE-AUGUST
 

OUR PROGRESS
-Completed the pedestrian ramps and sidewalk on the south side of 6th St. and Wells St.
-Removed and restored the pedestrian ramp and sidewalk at the southwest corner of N. Vel R. Phillips Ave. and Wells St. 
-Removed the existing concrete at the northwest corner of N. Vel R. Phillips Ave. and Wells St.; drainage and electrical work is underway
-Rebuilt the sidewalk, curb and pedestrian ramps on the south side of Wells St. from N. Old World Third St. to N. Plankinton Ave.
-Poured concrete curb and completed drainage work at Postman’s Square; electrical work is underway

LOOKING AHEAD
-Complete electrical work at Postman’s Square with restoration to follow
-Install electrical conduit for street lights and traffic signals across Wells St. at N. Vel R. Phillips Ave., N. 2nd St. and Plankinton Ave.
-Continue sidewalk removals on the north side of Wells St. from N. 2nd to N. 6th streets
-Begin sidewalk removals between N. Plankinton Ave. and the bridge 
-Finish driveway work in coordination with property owners

CONSTRUCTION IMPACTS
-On-street parking is restricted
-Short-term disruptions will occur when sidewalks and driveway approaches are being removed and rebuilt
-The installation of electrical conduit will require temporary lane closures 
-Access to businesses, residences, and other properties will remain open
-All work is weather dependent and subject to change

PROJECT SUMMARY

The rehabilitation project of West Wells Street from North 6th Street to North Broadway will consist of milling the existing asphalt pavement and replacing it with a new asphalt surface; curb, gutter and sidewalks will be replaced where necessary and utility improvements will be made to drainage structures, traffic signals and signs, and street lighting. Side street improvements to North 2nd Street and North Plankinton Avenue are included with the project. Once completed, the roadway will provide for an 11-foot driving lane and variable width shared parking/bicycle accommodations in each direction. 

WHAT TO EXPECT DURING CONSTRUCTION

The City of Milwaukee works to minimize impact for businesses, residents and the traveling public during construction. Work will take place over two stages to maintain two-way traffic, one lane in each direction:

Stage 1: The curbed side portions of the roadway will be constructed with two-way traffic, one lane in each direction, maintained in the center of the roadway. 

Stage 2: The center of the roadway will be constructed and two-way traffic, one lane in each direction, will be maintained on the curb side portions of the roadway. 

>>Both stages of construction will work with the detour route set up for the adjacent Wells Street Bridge construction. This detour routes traffic to Kilbourn Avenue via Water Street and Old World 3rd Street. 

Parking: On-street parking will be temporarily removed during construction. 

Driveway Access: City staff and the contractor will work to minimize the amount of time any driveway access is restricted and will notify property owners 48 hours in advance of any driveway work. 

Pedestrian Access: Pedestrian access will be maintained to abutting properties and businesses during construction with the least amount of inconvenience. 

Riverwalk Access: The Riverwalk will be closed intermittently at the bridge to pedestrians to accommodate construction. Other areas of the Riverwalk will remain open. The adjacent Wells Street Bridge construction detour routes pedestrians to either Kilbourn Avenue or Wisconsin Avenue. 

Bus Routes: Information for the 49 and 143 Flyers and Route 19 can be viewed here.

Construction Hours: Work is allowed from 7 a.m. to 9 p.m.
 


PROJECT CONTACTS
Tony Kotecki Construction Supervisor akotec@milwaukee.gov 414-708-3886
Megan O'Connor Support for Business Liaison moconnor@milwaukee.gov 414-708-1433

 

Start Date: June 1, 2018
Anticipated Completion: November 2018
*All work is weather dependent and subject to change

Construction Update
August 2018

Project Overview-Printable version

Public Involvement Meetings
The City of Milwaukee Department of Public Works conducted two public invovlement meetings to receive input and share project details with residents and businesses located in the project area.

September 28, 2016
City Hall 
200 East Wells Street, Room 301-B
6:00 - 8:00 p.m.

September 28, 2017
Frank P. Zeidler Municipal Building
841 North Broadway
Room 102
4:30 - 6:30 p.m.