NORTH TEUTONIA AVENUE RECONSTRUCTION PROJECT

CONSTRUCTION UPDATE

Storm sewer work will take place over the next three weeks. To accelerate the overall project schedule, we will complete storm sewer work planned for stage 2, while crews are out there now. The contractor will start at N. Teutonia Ave and N. 20th St., and will work south toward W. Groeling Ave, block by block. There will be day-time northbound traffic restrictions in the direct area where crews are working and that segment of the northbound lane will re-open at the end of each day. Local access to businesses will be allowed in the northbound lane/work zone. By the end of March 27th, water hydrant alterations, catch basin and lateral adjustments will be complete. (Added 3/26/20)

PROJECT OVERVIEW

The reconstruction project of North Teutonia Avenue from West Groeling Avenue to West Capitol Drive will consist of removing the deteriorated pavement and replacing it with new concrete pavement, curb & gutter, driveway approaches and sidewalk. Street lighting and traffic signals will be updated and storm sewer inlets and laterals will be replaced as needed. Once completed, the roadway will accommodate one driving lane, parking lane and a bicycle lane in each direction. 

The majority of the project is scheduled to be complete in December 2020 with landscape and electrical work planned in 2021.

WHAT TO EXPECT DURING CONSTRUCTION

TRAFFIC
To minimize how construction will impact residents, businesses, and the traveling public, the project will be split into two major stages.

Stage 1: The southbound lane of North Teutonia Avenue will be closed for construction. Majority of the side streets on the west side of the project will be closed. One lane of northbound traffic and on-street parking will be maintained on the east side of the roadway. There will be parking restrictions during some utility and concrete pavement operations. 

The following intersections will be open to east-westbound through traffic: W. Chambers St. and W. Capitol Dr.

Eastbound traffic on W. Nash St. and westbound traffic on W. Melvina St. will be maintained

Stage 2: The northbound lane of North Teutonia Avenue will be closed for construction. Majority of the side streets on the east side of the project will be closed. One lane of southbound traffic will be maintained on the newly completed roadway. On-street parking will be restricted. 

W. Capitol Dr. will be open to east-westbound through traffic. Westbound traffic on W. Chambers St. and eastbound traffic on W. Nash St. will be maintained. 

PARKING
In addition to on-street parking during Stage 1, a temporary parking lot will be provided at the corner of W. Nash St. and N. Teutonia Ave. for residents and customers to continue to support the local businesses throughout construction. To access the parking lot

Stage 1: Travel northbound on N. 20th St., turn right at W. Nash St. 
Stage 2: Travel southbound on N. Teutonia Ave., turn right at W. Nash St. 

SIDEWALK
Pedestrian access will be maintained to abutting properties during construction with the least amount of inconvenience. Short-term disruptions will occur when sidewalks are being removed and rebuilt.

Stage 1: East-west pedestrian crossings through the work zone will be maintained at the following intersections: Chambers, Nash and Melvina

Stage 2: East-west pedestrian crossings through the work zone will be maintained at the following intersections: Chambers and Vienna
*Over the course of the project, changes may occur to the pedestrian crossing locations. 

DRIVEWAY ACCESS

Residential driveways: Access will be restricted in the work zone. Temporary overnight parking permit instructions will be provided to those affected. 

Commercial driveways: There will be disruptions to driveway access such as when the contractor is breaking and removing pavement, grading, putting in the curb and gutter, and paving. Project staff will notify property owners 48 hours in advance when any driveway is being removed and rebuilt. 

BUS
Route 12: Will detour off of Teutonia between Locust and Atkinson. Buses will use 7th Street during this time.

Route 60: Will detour off of Burlegh between Hopkins and 7th. Buses will use Locust during this time.

CONSTRUCTION HOURS
Work is allowed Monday through Friday from 7:00 a.m. to 9:00 p.m. The sawing of the mainline concrete pavement outside of those hours will be allowed due to the fact it has to be completed right after initial set and before random cracking occurs. The placement of the mainline concrete pavement is a critical milestone in keeping these large paving projects on schedule. Any work scheduled on weekends will need approval from the Department of Public Works. 


PROJECT CONTACTS

Lynn Des Jardins Construction Supervisor ldesja@milwaukee.gov 414-708-3885
Paul Grabowski Project Inspector paul.grabowski@milwaukee.gov 414-708-3835
Megan O'Connor  Project Liaison moconnor@milwaukee.gov 414-708-1433

Sign up to receive construction updates-email moconnor@milwaukee.gov 

 

Start: March 16, 2020
End: December 2020
*All work is weather dependent and subject to change

Project Overview

Public Involvement Meeting
The City of Milwaukee Department of Public Works held a public involvement meeting to receive input and share project details with residents and businesses located in the project area. 

June 15, 2017
Siloah E.V. Lutheran Church
3721 North 21st Street
5:30 p.m. to 7:30 p.m.