The City of Milwaukee Department of Public Works and State of Wisconsin Department of Transportation are planning to replace East Wells Street from North Broadway to North Prospect Avenue (.44 mile). The scope of work includes removing and replacing deteriorated pavement, curb & guttter, driveway approaches and sidewalk. Pedestrian curb ramps will be built to meet ADA compliance, and we will enhance pedestrian and bike accommodations. Drainage structures, street lighting and traffic signals will also be upgraded.
Estimated construction cost is $5.5 to $6.0 million dollars. Approximate Breakdown:
Preliminary Engineering
Construction Costs
EXISTING CONDITIONS
We are currently in the design phase through 2022. Construction is tentatively scheduled for 2023.
The City of Milwaukee Department of Public Works holds public involvement meetings to receive input and share project details with residents and businesses located in the project area.
Virtual Public Involvement Meeting #1 – February 9, 2021 from 5:00 pm to 7:00 pm
The purpose of the 1st public meeting is to introduce the project, and gather community experience to start design options. We want you to tell us: How do you get around your neighborhood and where are you going? What problems do you see and experience, while walking, driving, or riding a bike? What do you like about the current street? What dont you like about it? Where is it difficult or dangerous to cross the street? What do you want to see on Wells Street?
To join on your computer or mobile app - Click here to join the meeting
If you prefer to call in (audio only): 414-251-0392 and enter code 61567128#
Public Involvement Meeting #2 - Summer 2021
Purpose: Provide traffic data, and show feasible design options based on initial community feedback, and design work
We want you to tell us: How do the proposed designs work for you? Do the proposed designs capture what the community wants? Are we missing anything?
Pre-Construction Meeting - Early Spring 2023
Purpose: Outline construction schedule, staging details, and address concerns of expected impacts
Let us know where you see issues and opportunities for improvement on East Wells Street! Your input will help shape how the road looks and will help identify solutions to make the street safer and more enjoyable for walking, bicycling, and driving.
Name
Address
Email
Comment box
Thank you for taking the time to provide your feedback and comments!
Nicholas Goodwin Project Manager ngoodw@milwaukee.gov 414-286-0461