Bookmark and Share

Project Summary

West Lapham Boulevard (from 1st to 11th)

This project involves the area on West Lapham Boulevard from South 1st Street to South 11th Street. Work includes removing the existing pavement surface and replacing it with a new layer of asphalt. Curb and gutter, sidewalk and driveway approaches will be replaced where necessary due to grade and/or condition. The contractor plans to begin work in early July. The project is expected to be completed by the end of September.

Project Update:  September 15, 2010

The asphalt resurfacing project on West Lapham Boulevard from South 1st Street to South 11th Street has been completed. The existing pavement surface was removed and replaced with a new layer of asphalt. Curb and gutter, sidewalk and driveway approaches were replaced where necessary due to grade and/or condition. The construction is done and the street is open to traffic.